Prestige Pulimamidi Project Schedule

Featured Image of Prestige Pulimamidi Project Schedule


Prestige Pulimamidi is a 74-acre plotted development by Prestige Group. It is in Pulimamidi, Telangana, on the southern Hyderabad corridor near the Outer Ring Road. The project has 1,100 luxury plots from 1,200 to 2,400 sq ft. The pre-launch opened before January 2027. The formal launch is on 10 January 2027. Infrastructure work follows across 8 milestone stages from launch to December 2030 possession. This page covers the full project schedule.

Project Schedule at a Glance


Milestone Target
Pre-launch opens Before January 2027
Formal launch and RERA registration 10 January 2027
Boundary wall and site clearing Early 2027
Internal roads and plot demarcation (1,100 plots) Mid 2027
Water supply and underground drainage network Late 2027
Electrical supply lines to each plot Early–Mid 2028
Street lighting and entry gate infrastructure Mid–Late 2028
Open-space zone (~9.84 acres) and amenities 2029
Layout completion certificate and possession December 2030

Payment milestones are tied to infrastructure progress. The official possession date is December 2030.

Stage 1 — Pre-Launch and RERA Registration (2026–Jan 2027)


The pre-launch phase opened before the January 2027 launch. Buyers register interest and pay a booking amount during this period. They get priority plot selection at the formal January 2027 launch.

The formal launch is on 10 January 2027. Telangana RERA registration is expected at the launch. RERA confirmation is mandatory before sale agreements are signed. No physical work starts before the January 2027 launch.

Stage 2 — Boundary Wall and Site Clearing (Early 2027)


The first visible work on the 74-acre Pulimamidi site is the perimeter boundary wall. This secures the full site before any internal work begins. Site clearing and ground levelling follow where required.

At 74 acres, the boundary wall covers a large perimeter. Completing it early defines the township boundary and protects the plot area.

Stage 3 — Internal Roads and Plot Demarcation (Mid 2027)


The internal road network is laid across the 74-acre township. Roads connect all 1,100 plots and the central open-space zone. Each of the 1,100 plots is marked on the ground with corner markers as per the approved layout plan.

The three plot types — 1,200 sq ft, 1,600 sq ft, and 2,400 sq ft — are demarcated at this stage. Roads are wide and well-spaced for a township of this scale.

Stage 4 — Water Supply and Drainage (Late 2027)


Underground water supply and drainage lines are installed along all internal roads. Each plot gets a water connection point at its boundary. The stormwater drainage network handles rainfall across all 74 acres.

Underground utilities are laid before road surfaces are finalised. This avoids cutting up finished roads later.

Stage 5 — Electrical Supply to Plots (Early–Mid 2028)


Underground HT and LT electrical lines are laid from the substation to each of the 1,100 plots. Each plot gets a power connection point at its boundary. Buyers can connect to grid power at possession without running long supply lines across the site.

Stage 6 — Street Lighting and Entry Gate (Mid–Late 2028)


Street lighting poles and fixtures go up along all internal roads. The main entry gate, security booth, and access barriers are built at this stage. Internal signage and road markings are completed.

The entry gate and street lighting bring the township to a visible level of completion. This is the stage buyers see as the project taking its final shape.

Stage 7 — Open-Space Zone and Amenities (2029)


Prestige Pulimamidi dedicates approximately 9.84 acres to open green spaces. This covers parks, green buffers, and open areas within the township. The open-space zone is landscaped and fitted out at this stage.

The amenity areas within the open zone are completed here. The large 74-acre township gives residents generous common land around the 1,100 plots.

Stage 8 — Layout Completion and Possession (December 2030)


The Telangana government issues the layout completion certificate once all infrastructure meets the approved plan. Plot owners receive possession with all roads, utilities, and the open-space zone in place.

After possession, buyers may begin construction of their own homes. Construction must follow local municipal approvals and the setback rules in the approved layout plan.

About the Project


Prestige Pulimamidi is in Pulimamidi, Telangana. Rajiv Gandhi International Airport is 20.9 km away. LB Nagar Metro Station (Blue Line) is 23.6 km away. Shadnagar Railway Station is 20.3 km away. Pulimamidi Bus Stop is 2.5 km away. The Outer Ring Road connects the township to Hyderabad city. Plots range from Rs 96 Lakhs (1,200 sq ft) to Rs 1.92 Crores (2,400 sq ft) at Rs 8,000 per sq ft.

FAQs


1. When does work start at Prestige Pulimamidi?

Physical work starts after RERA registration and formal launch on 10 January 2027. Site clearing and the boundary wall begin first. Internal road layout and plot demarcation for the 1,100 plots follow in mid 2027.

2. How many milestones does the project have?

The project has 8 payment milestones. Each milestone is linked to an infrastructure stage — from site clearing and roads to utilities, street lighting, and the 9.84-acre open-space zone. Payment is released as each stage is completed.

3. What is the RERA status of Prestige Pulimamidi?

Telangana RERA registration is expected at the formal launch on 10 January 2027. It has not yet been applied for. Verify the status on ts-rera.telangana.gov.in after the January 2027 launch. Do not sign the sale agreement before RERA is confirmed.

4. What is the possession date at Prestige Pulimamidi?

The possession date is December 2030. Infrastructure work covers 8 milestones across approximately 3 years from the January 2027 launch. Verify the official date on ts-rera.telangana.gov.in after registration.

5. Can I build a home on my plot after possession?

Yes. After possession, you may build a home on your plot. Construction must follow the approved building plan and local municipal bye-laws. The township delivers roads, utilities, and open spaces before possession.

6. Can buyers track infrastructure progress on RERA?

Yes. Once registered, Prestige Group must update the Telangana RERA portal every quarter. Go to ts-rera.telangana.gov.in and search the project RERA number after the January 2027 launch. Each quarterly update shows the completion percentage for each infrastructure stage.